2024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (2024)

City of Brooklyn Park

City of Brooklyn Park sent this email to their subscribers on June 21, 2024.

Update email for the 2024 West River Road MSA Overlay project.

2024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (1)

June 21

Welcome to the weekly construction updates for the 2024 West River Road MSA Overlay project happening in your neighborhood. We want to keep you as updated as possible, so we will send these emails every week until construction is complete.

Project Overview

CIP 4002-24 West River Road Municipal State Aid Overlay project runs between Brookdale Drive and Newton Avenue. This overlay project includes replacing the asphalt road surface (upper 2 inches), spot replacements of curb and gutter, storm sewer and water rehabilitation.

Traffic Control

The work on West River Road between Brookdale Drive and Newton Avenue will be done under one-way traffic SOUTHBOUND with the west side of West River Road closed off to accommodate the construction. The detour route for NORTHBOUND West River Road will be TH 252 to TH 610 to Noble Parkway to 97th Avenue, residents can also use 85th Ave if they live on West River Road south of 85th. Please see link of detour map.

SOUTHBOUND traffic will only be allowed throughout the entire time of construction even when the construction zone switches from the east side to the west side of West River Road.

NORTHBOUND traffic will be detoured throughout the entire time of construction.

Traffic control is set up to provide a safe work zone for the contractor and the travelling public. Please use caution and slower speeds while driving through the project. The construction workers appreciate that.

Detour Map

View map of Detour >

Construction Schedule through June 28

  • Construction work zone is set up on the west side.
  • The contractor will continue to remove and replace concrete curb and gutter.

Construction Schedule Starting the Week of July 1

  • The contractor will be continuing to replace concrete curb and gutter.

Mailboxes

  • We will need to set up temporary mailboxes just off West River Road for the safety of the postal delivery person and to allow traffic to freely travel. Please watch for a notification today from the contractor about switching your mail from your permanent mailbox to the temporary mailbox. They will also let you know where the location of the temporary mailbox will be. Once construction is completely done, they will deliver mail to your permanent mailbox again.

Garbage Containers

  • All containers will need to be placed on the east side of the work zone so they can be picked up from the passenger side of the vehicle travelling down the one-way traffic lane.

Irrigation Systems

  • If you have an irrigation system that was damaged due to the work from the contractor please contact Nate Musial so we can get that fixed

Construction Map

View map of the construction project >

Emergency contact after hours

If you have an emergency related to the project after work hours or on weekends, please call 911. The Police Department will notify the 24 hour on-call project superintendent from the contractor.

Construction hours

  • Monday – Friday, 7 AM - 8 PM
  • Saturday, 8 AM - 7 PM
  • The contractor said they plan on working 7am-7pm M-F. The hours above are the acceptable hours of construction in Brooklyn Park without written consent of the City Engineer. Emergencies and special considerations may require work outside of the normal construction hours.

Sign up for Email Updates

If you would like to get weekly updates about the progress of this project, please subscribe to our emails at

  • Select “2024 MSA Mill & Overlay”
  • Or, email Jason Ives at [emailprotected] and he will get you signed up.

Questions?

Nate Musial (first point of contact)
Project Inspector, City of Brooklyn Park
612-834-4206
Email Nate Musial

Craig Runnakko
Construction Engineer, City of Brooklyn Park
763-493-8109
Email Craig Runnakko

Mitch Robinson
Interim City Engineer, City of Brooklyn Park
763-493-8291
Email Mitch Robinson

If you need this information in another language or format or disability accommodations, email[emailprotected] or call 763-424-8000.

Si usted necesita esta información en español: 763-424-8000

Yog xav tau kev pab, thov hu rau 763-424-8000 lawv mam li nrhiav ib tus neeg txhais lus rau koj

2024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (2)

Stay Connected with City of Brooklyn Park:

2024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (3)2024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (4)2024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (5)2024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (6)
This email was sent to [emailprotected] using GovDelivery Communications Cloud on behalf of: City of Brooklyn Park ·5200 85th Ave., N. · Brooklyn Park, MN 554432024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (7)

Text-only version of this email

Update email for the 2024 West River Road MSA Overlay project.Header-streetsWEST RIVER ROAD MSA OVERLAYJUNE 21Welcome to the weekly construction updates for the 2024 West River Road MSA Overlay project happening in your neighborhood. Wewant to keep you as updated as possible, so we will send these emails every week until construction is complete.----------------------------------------------------------------------------------------------------------------------------------PROJECT OVERVIEWCIP 4002-24 West River Road Municipal State Aid Overlay project runs between Brookdale Drive and Newton Avenue. This overlayproject includes replacing the asphalt road surface (upper 2 inches), spot replacements of curb and gutter, storm sewer and waterrehabilitation.TRAFFIC CONTROLThe work on West River Road between Brookdale Drive and Newton Avenue will be done under one-way traffic SOUTHBOUND with the westside of West River Road closed off to accommodate the construction. The detour route for NORTHBOUND West River Road will be TH 252to TH 610 to Noble Parkway to 97th Avenue, residents can also use 85th Ave if they live on West River Road south of 85th. Pleasesee link of detour map.SOUTHBOUND traffic will only be allowed throughout the entire time of construction even when the construction zone switches fromthe east side to the west side of West River Road.NORTHBOUND traffic will be detoured throughout the entire time of construction.Traffic control is set up to provide a safe work zone for the contractor and the travelling public. Please use caution and slowerspeeds while driving through the project. The construction workers appreciate that.DETOUR MAPView map of Detour >CONSTRUCTION SCHEDULE THROUGH JUNE 28 * Construction work zone is set up on the west side. * The contractor will continue to remove and replace concrete curb and gutter.CONSTRUCTION SCHEDULE STARTING THE WEEK OF JULY 1 * The contractor will be continuing to replace concrete curb and gutter.MAILBOXES * We will need to set up temporary mailboxes just off West River Road for the safety of the postal delivery person and to allow traffic to freely travel. Please watch for a notification today from the contractor about switching your mail from your permanent mailbox to the temporary mailbox. They will also let you know where the location of the temporary mailbox will be. Once construction is completely done, they will deliver mail to your permanent mailbox again.GARBAGE CONTAINERS * All containers will need to be placed on the east side of the work zone so they can be picked up from the passenger side of the vehicle travelling down the one-way traffic lane.IRRIGATION SYSTEMS * If you have an irrigation system that was damaged due to the work from the contractor please contact Nate Musial so we can get that fixedCONSTRUCTION MAPView map of the construction project >EMERGENCY CONTACT AFTER HOURSIf you have an emergency related to the project after work hours or on weekends, please call 911. The Police Department willnotify the 24 hour on-call project superintendent from the contractor.CONSTRUCTION HOURS * Monday – Friday, 7 AM - 8 PM * Saturday, 8 AM - 7 PM * The contractor said they plan on working 7am-7pm M-F. The hours above are the acceptable hours of construction in Brooklyn Park without written consent of the City Engineer. Emergencies and special considerations may require work outside of the normal construction hours.SIGN UP FOR EMAIL UPDATESIf you would like to get weekly updates about the progress of this project, please subscribe to our emails at * Select “2024 MSA Mill & Overlay” * Or, email Jason Ives at [emailprotected] and he will get you signed up.----------------------------------------------------------------------------------------------------------------------------------QUESTIONS?Nate Musial (first point of contact)Project Inspector, City of Brooklyn Park612-834-4206Email Nate MusialCraig RunnakkoConstruction Engineer, City of Brooklyn Park763-493-8109Email Craig RunnakkoMitch RobinsonInterim City Engineer, City of Brooklyn Park763-493-8291Email Mitch RobinsonIf you need this information in another language or format or disability accommodations, email[emailprotected] or call763-424-8000.Si usted necesita esta información en español: 763-424-8000Yog xav tau kev pab, thov hu rau 763-424-8000 lawv mam li nrhiav ib tus neeg txhais lus rau kojStay Connected with City of Brooklyn Park: Facebook Twitter Youtube RSS Feed ----------------------------------------------------------------------------------------------------------------------------------This email was sent to [emailprotected] using GovDelivery Communications Cloud on behalf of: City of Brooklyn Park ·5200 85thAve., N. · Brooklyn Park, MN 55443 GovDelivery logo

Show all

The Latest Emails Sent By City of Brooklyn Park

2024 West River Road MSA Overlay update: June 21
Road Reconstruction Weekly Update (June 21)
REMINDER: Homeowners Association (HOA) Workshop
63rd Avenue Trail and MSA Overlay weekly update: June 17

More Emails, Deals & Coupons From City of Brooklyn Park

63rd Avenue Trail and MSA Overlay weekly update: April 26
Upcoming FAFSA Navigator Training
City of Brooklyn Park Job opportunities Update
City of Brooklyn Park Job opportunities Update
Apply for the Brooklyn Park Development Corporation Board!
Homeowners Association (HOA) Workshop
City of Brooklyn Park Job opportunities Update
Run for City Council!
National Night Out 2024
Recycling Week and Recycling at Your Event

Email Offers, Discounts & Promos From Our Top Stores

deadline hollywood'Rust' Armorer Doesn't Have To Testify At Alec Baldwin's Involuntary Manslaughter Trial, Judge Rules; Actor Fails Again To Get Case Dismissed
all american butterSOLD OUT: Restocking Soon ⏰
bigovenEasy Dressed Up Guacamole + Weekly Menu
fightersTop Ten Headgear - PRE ORDER ONLY!
saks fifth avenueHere are new picks from Theia
mhaTips if you hate your architecture job; Major Centre Pompidou overhaul by Moreau Kusunoki and Frida Escobedo; Legacy of Woodbury University San Diego; AI flaws in Midjourney Islamic architecture images
uniform studiosCELTIC PACK NOW AVAILABLE!
bizpac reviewSwanky NYC club frequented by celebs, politicians BOOTS conservative member after Father’s Day post
deadline hollywoodABC's 'High Potential' Sets Todd Harthan As New Showrunner
shopsk🔴 NEW Hennessy XO NBA! 💸 🔴 Hibiki on Sale!
home of wool🥱 Fed up with waking up with neck pain? 🥱
the sacramento beeStart building your future today with a private student loan from SoFi
2024 West River Road MSA Overlay update: June 21 - City of Brooklyn Park (2024)
Top Articles
Latest Posts
Article information

Author: Lidia Grady

Last Updated:

Views: 6169

Rating: 4.4 / 5 (65 voted)

Reviews: 88% of readers found this page helpful

Author information

Name: Lidia Grady

Birthday: 1992-01-22

Address: Suite 493 356 Dale Fall, New Wanda, RI 52485

Phone: +29914464387516

Job: Customer Engineer

Hobby: Cryptography, Writing, Dowsing, Stand-up comedy, Calligraphy, Web surfing, Ghost hunting

Introduction: My name is Lidia Grady, I am a thankful, fine, glamorous, lucky, lively, pleasant, shiny person who loves writing and wants to share my knowledge and understanding with you.